May 2012

Contractors sued for False Claims Act violations face a potential judgment assessing stiff civil penalties and treble damages. Even assuming that the government can meet its burden of proving a violation of the False Claims Act, defenses to the damages elements of the case should not be ignored. Grossly disproportionate penalties One important limit on the assessment of civil penalties appears in the 8th Amendment to the United States Constitution, which prohibits the assessment of excessive fines. To prevail on an 8th Amendment defense, a contractor must show that the fine would be grossly disproportionate to the gravity of the offense. Four factors are relevant here:

  1. the extent of the harm caused;
  2. the gravity of the offense relative to the fine;
  3. whether the violation was related to other illegal activity, and the nature and extent of that activity; and
  4. the availability of other penalties and the maximum penalties which could have been imposed.

In one recent case, the court accepted an 8th Amendment argument that wiped out a $50 million civil penalty against a contractor found guilty of bid rigging. See United States ex rel. Bunk v. Birkart Globistics GMBH & Co., No. 1:02cv1168, 1:07cv1198 (E.D. Va. Feb. 14, 2012). The contract involved moving services for military personnel stationed in Europe. The contractor submitted a bid with 51 line item prices. The court found a violation of the False Claims Act because one of the line item prices was affected by a subcontractor bid-rigging scheme. The government sought to assess a $5,500 penalty for each of the contractor’s 9,136 invoices, yielding a penalty of $50,248,000. Despite the False Claims Act violation, the court refused to assess the penalty because it was grossly disproportionate to the gravity of the offense. The entire contract price was only $3.3 million and the contractor’s profit was only $150,000. There was no evidence of economic harm to the government because the contractor’s services were acceptable and the prices were lower than any competitor’s prices.

On May 18, 2012, the United States House of Representatives voted 299-120 to approve HR 4310, the National Defense Authorization Act for Fiscal Year 2013 [pdf]. The House vote rejects two amendments that had been the topic of some discussion within the government contracts community. One would have restricted the definition of “commercial item”

The Contractor’s Perspective is up to three entries on the application of FAR 52.204-10, which requires some federal contractors and first-tier subcontractors to report the compensation of their top-five highest paid executives. Even though it has been almost two years since the requirement first appeared in the FAR, the topic still generates a lot of interest and a lot of questions. Here are answers to some of the questions we received in the executive compensation reporting segment of our recent webinar on Transparency in Government Contracting. We hope you find them useful.

Question: Does FAR 52.204-10 apply only to new contracts or does it also apply retroactively to existing contracts?

Answer: Even though the statutory requirement for reporting executive compensation became law in April 2008 when President Bush signed the Government Funding Transparency Act of 2008, the contractual requirement didn’t go into effect until July 8, 2010, when the FAR Councils published FAR 52.204-10 as an “interim rule.” According to the text of the interim rule, FAR 52.204-10 is required in all contracts over $25,000 that are awarded after July 8, 2010. It does not apply to contracts awarded before on or before July 8, 2010.