The contractor’s duty to proceed with performance pending the resolution of disputes is a basic concept in the law of government contracts. It is laid out explicitly in FAR 52.233-1(i), the mandatory disputes clause that appears in nearly all federal contracts: “The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under the contract, and comply with any decision of the Contracting Officer.”

But the duty to proceed has important limits. A contractor is excused from its duty to proceed and may stop work if the government materially breaches its own obligations under the contract.

Breaches occur in many contexts. A cardinal change in the scope of work is a breach that excuses a contractor’s performance. Terminating a contract just to get a lower price is a breach. Refusing to pay for a contractor’s work without an adequate excuse is also a breach.

According to the decision in Kiewit-Turner v. Dep’t of Veteran Affairs, CBCA No. 3450 (Dec. 9, 2014) [pdf], the government breaches the contract by ordering a contractor to continue performance when it is clear that there will be no funds available to pay for the work. The Civilian Board of Contract Appeals recognized Kiewit-Turner‘s right to stop work when the Department of Veteran Affairs failed to provide a design that would have allowed construction to be completed within the budget established by the available appropriations. Despite the general duty to proceed, Kiewit-Turner was not required to continue performance because it was clear that the construction costs would exceed the available funds and the VA refused to seek additional funding or incorporate value engineering changes to reduce the overall construction cost.

If you are getting ready to submit a claim on a federal contract—especially one that challenges an assessment of liquidated damages—take note of the Federal Circuit’s decision in K-Con Building Systems, Inc. v. United States, No. 2014-5062 (Fed. Cir. Feb. 12, 2015) [pdf]. It has some specific instructions for the contents of your claim letter and demonstrates the harsh results that follow from a misstep in the disputes process.

K-Con held a Federal Supply Schedule contract for prefabricated structures. In 2004, it won a $582,000 Coast Guard task order for the design and construction of a Coast Guard cutter support building at Port Huron, Michigan.

K-Con’s July 2005 Claim

When K-Con was unable to complete the work by the deadline set forth in the task order, the Coast Guard assessed liquidated damages of $109,554—186 days at $589 per day. On July 28, 2005, K-Con submitted a one-page claim letter seeking remission of the liquidated damages.

Although it was brief, K-Con’s letter asserted three reasons why the liquidated damages assessment was improper:

  1. K-Con “was not the sole cause of any alleged delays” and any K-Con delays were “concurrent with delays caused by the government;”
  2. the government “failed to issue extension to the completion date as a result of changes to the contract by the government;” and
  3. the liquidated damages “are an impermissible penalty.”

K-Con’s letter requested a contracting officer’s final decision. Though it demanded relief of more than $100,000, K-Con’s letter asserted that a certification was not required “since the assessment of liquidated damages is a claim by the Government.”

Despite getting a rare Writ of Mandamus from the D.C. Circuit Court of Appeals establishing that its internal investigations were covered by the attorney-client privilege, Kellogg Brown & Root must still turn them over. As predicted in our earlier posts on Barko v. Halliburton, Judge James Gwin has ruled that KBR waived the attorney-client privilege that would otherwise have shielded KBR’s internal investigation documents from discovery. His rationale is reflected in three opinions published in November and December 2014.

In a June 2014 opinion, the D.C. Circuit held that KBR’s internal investigation documents would be privileged if obtaining or providing legal advice was “a primary purpose of the communication, meaning one of the significant purposes. . . .”

But the Court of Appeals also invited the District Court to consider additional arguments that might have been timely asserted as to “why these documents are not covered by either the attorney-client privilege or the work product doctrine.”

That is what Judge Gwin did. When the case returned to the District Court, Barko sought “interviews, reports, and documents that KBR prepared while investigating tips KBR had received that involved the same allegations found in Barko’s complaint.” Barko relied on four arguments to support his claim that KBR had waived any attorney-client privilege or work-product protection over the documents:

  1. KBR put the contents of the documents at issue in the litigation;
  2. KBR’s Rule 30(b)(6) witness reviewed the privileged documents prior to testifying at his deposition;
  3. The documents fell under the crime-fraud exception to the privilege; and
  4. KBR had failed to list these documents on a privilege log when responding to an earlier administrative subpoena from the Defense Criminal Investigative Service (“DCIS”).

In an opinion issued on November 20, 2014, Judge Gwin accepted the first two arguments.


Submitted by Husch Blackwell Associate Kayt Kopen

Federal contractors will soon need to update their Equal Employment Opportunity policies and their Affirmative Action Plans. According to an announcement by DOL’s Office of Federal Contract Compliance Programs, federal contracts and subcontracts awarded or modified after April 8, 2015, must include new contract language prohibiting discrimination

Contractors receive about $50 billion a year through GSA multiple award schedule contracts. With that level of spending, it is easy to see why GSA has adopted policies and procedures that allow it to secure the best possible pricing for each one of its schedule contracts.

Initially, GSA uses discounts, terms, and conditions that contractors offer to other customers to negotiate “most favored customer” pricing.

But negotiated prices stated in a schedule contract are not necessarily fixed for the entire term of the contract. The contractor remains subject to the Price Reductions Clause (GSAR 552.238-81; formerly GSAR 552.238-75), which imposes a duty to report certain changes in its commercial pricing terms. Under some circumstances, the PRC allows a downward adjustment in the contractor’s fixed prices.

Two triggers for adjustments under the PRC

Two types of events will trigger the Price Reduction Clause. The first is relatively straightforward: GSA and the contractor base the federal supply schedule pricing on a commercial price list, catalog, schedule, or similar document. The contractor later reduces the list price or otherwise revises the price list or offers more favorable pricing, discounts, or terms to another customer.  When that occurs, the contractor must offer the same reduced price, discount, or better terms to the government.

The second situation is a bit trickier. The PRC is triggered when the contractor makes a pricing change that disturbs the relationship between the government’s pricing and the pricing offered to the customer or customers whose pricing terms are established as the “basis of award.”

Calling the Voyager fuel card program unmanageable and uneconomic, the USPS Office of Inspector General recommends that the Postal Service use another method to manage fuel under its HCR contracts. In its advisory report dated September 30, 2014, the OIG concludes that the Voyager fuel card program has cost more money that it saved and discourages fuel efficiency. The Postal Service spent $5.1 billion for 1.6 billion gallons of fuel for Highway Contract Route (HCR) contracts under the program over the last nine years.

The Senate passed the Carl Levin and Howard P. “Buck” McKeon National Defense Authorization Act for Fiscal Year 2015 [pdf] on Friday, December 12, 2014. President Obama is expected to sign the bill into law. The $585 billion bill authorizes the Pentagon’s activities in FY 2015. It includes $521.3 billion in base defense spending and another $64 billion in war funding. Here is a summary of the procurement reform initiatives that will be relevant to contractors in the upcoming year:

  1. Cyber incident reporting for operationally critical contractors. Section 1632 of the 2015 NDAA directs the Secretary of Defense to designate and notify “operationally critical contractors,” a term narrowly defined in the bill. After notification, designated contractors will be required to report to the Department of Defense each cyber incident with respect to any network or information system of such contractor. Reports must include: an assessment of the effect on the contractor’s ability to meet the Department’s contractual requirements; the technique used in the cyber incident; any sample of malicious software obtained; and a summary of information compromised by the incident. Despite the disclosure requirement, section 1632 provides for protection of contractor trade secrets and confidential commercial or financial information. It also limits the dissemination of information obtained to relevant entities and agencies.
  2. Enhanced authority for non-DOD Chief Information Officers. Section 831 of the NDAA increases the role of Chief Information Officers of agencies other than the Department of Defense. It provides that an agency may not enter into a contract for information technology unless the contract has first been reviewed and approved by the agency’s Chief Information Officer. The head of each covered agency must ensure that its Chief Information Officer has a significant role in all annual and multi-year planning, budgeting, and reporting related to information technology. The bill requires the Director of OMB and the Chief Information Officers of appropriate agencies to increase the efficiency and effectiveness of information technology investments and to develop opportunities to consolidate the acquisition and management of information technology services. The Chief Information Officer of each covered agency is directed to inventory agency data centers and develop a multi-year strategy for consolidation and optimization of those data centers inventoried.
  3. DOD CIO positions consolidated. Section 901 of the 2015 NDAA incorporates a DOD proposal to combine the positions of Chief Information Officer and Deputy Chief Management Officer into the position of Under Secretary of Defense for Business Management and Information. The new Under Secretary will oversee business operations, personnel, and IT projects and will be appointed by the President with the advice and consent of the Senate. This change will not take place until the next administration.