When selecting a photo to use on its popular “Liberty” stamps, the Postal Service unknowingly used a replica of the 128-year old Statue of Liberty. Instead of the original version welcoming the tired, the poor, and the huddled masses in New York harbor,  USPS selected the “fresh-faced,” “sultry” and “sexier” 17-year old version summoning merry-makers to the New York-New York Hotel & Casino in Las Vegas, NV. Robert Davidson, sculptor of the Sin City version of Lady Liberty, has thus filed a copyright infringement action in federal court, seeking unspecified damages.

The Contract Disputes Act imposes a six-year statute of limitations on all claims, whether they are asserted by the contractor or by the Government. See 41 U.S.C. § 7103(a)(4)(A). The limitations period begins to run upon accrual of a claim, which is “the date when all events . . . that fix the alleged liability of either the Government or the contractor and permit assertion of the claim . . . were known or should have been known.” FAR 33.201. Because six years must pass before the claim expires, the precise date of accrual is often little more than an academic question. Indeed, there have been relatively few cases applying the CDA limitations period to Government claims. But accrual has recently become a real and sometimes insurmountable obstacle to Government claims. Here is a short summary of the basic concepts that have emerged from the decisions that have addressed the issue.

1.         The government has the burden of proving timeliness. 

The CDA limitations period is “jurisdictional.” When the government asserts a claim against a contractor, the government has the burden of proving jurisdiction. To do so, the government must establish that the claim was timely asserted. If the government cannot show that the claim was asserted within six years of accrual, the Board or the Court lacks jurisdiction to hear the claim. Raytheon Missile Systems, ASBCA No. 58011 (Jan. 28, 2013) [pdf].

Let’s put the politics of the 2013 government shutdown aside and look at the practical questions. Like the government employees that are affected, contractors want to know if they should come to work. And if they do come to work, will they get paid? Will the options be exercised? Will their contract be terminated for

De-regulation of the U.S. Postal Service’s purchasing policies has stymied the prosecution of defective pricing fraud cases, according to a September 18, 2013 report issued by the USPS Office of Inspector General (OIG).  U.S. Attorney’s offices have thus declined to criminally prosecute suppliers for submitting defective cost or pricing data in procurement actions valued at $36 million. The OIG therefore recommends that the Postal Service require suppliers to certify that cost or pricing data are accurate, complete, and current. USPS management, however, disagrees. The Postal Service believes its interests are already fully protected and the disadvantages of imposing a new certification requirement would outweigh any benefits.

Under the OFCCP’s final rule announced on August 27, 2013, federal contractors and subcontractors that meet the applicability criteria will be required to meet new goals for hiring protected veterans and individuals with disabilities. For veterans, the new “benchmark” is based on the percentage of veterans in the civilian labor force (currently 8 percent) or

[UPDATE: On May 26, 2015, the Supreme Court reversed the Fourth Circuit’s decision in Carter and held that the Wartime Suspension of Limitations Act is limited to criminal offenses. Kellogg Brown & Root Services, Inc. v. Carter, No 12-1497 (U.S. May 26, 2015) [pdf]. Our discussion of the Carter decision is available here.]

What is the statute of limitations for qui tam actions brought against a contractor during a time of war? The answer to this question depends not only on whether the Wartime Suspension of Limitations Act applies to actions brought by an individual relator under the qui tam provisions of the False Claims Act, but also on when the United States is “at war.” The Fourth Circuit Court of Appeals addressed both of these questions in U.S. ex rel. Carter v. Halliburton Co., 710 F.3d 171 (4th Cir. 2013).

“At war” does not mean “declared war.”

The Wartime Suspension of Limtations Act was enacted in 1942. It suspends the applicable limitations period for any offense involving fraud against the United States when the country is “at war” or when Congress has enacted a specific authorization for the use of the Armed Forces. The suspension lasts for the duration of the war and until five years after hostilities end. 18 U.S.C. § 3287. Hostilities must be terminated “by a Presidential proclamation, with notice to Congress, or by a concurrent resolution of Congress.”

The meaning of “at war” is not specifically outlined in the WSLA, but it is a focal point of the decision in Carter. The relator, a water purification operator at two U.S. military camps in Iraq, asserted that his employer charged the government for work that was not performed. Due to a number of procedural obstacles, the action was filed outside of the six-year limitations period that normally applies to FCA qui tam actions. As a result, the district court dismissed the action as untimely. The relator appealed, asserting that the WSLA tolled the limitations period because the hostilities in Iraq meant that the United States was “at war.” The Fourth Circuit agreed, reasoning that a “formalistic” definition of when the country was “at war” did not reflect the “realities of today.”

The GAO’s decision in BC Peabody Constr. Serv., Inc., B-408023 (May 10, 2013) [pdf] illustrates the importance of establishing prejudice in a bid protest. The protester alleged that it proposed the same subcontractor (Bauer Foundation Corporation) as the awardee proposed on a dike rehabilitation project. Both offerors relied on Bauer for the “cut-off wall,” a critical element of the project. Both proposals showed that Bauer had the required experience for the cut-off wall.

Despite their use of the same subcontractor, the Corps of Engineers nevertheless assigned the awardee and the protester different scores for the cut-off wall element of their proposals. The Corps rated the awardee’s proposal acceptable for both the demonstrated experience and past performance subfactors, but it rated the protester’s proposal unacceptable.  The GAO agreed the Corps’s action was procurement error. “Where multiple proposals propose the same contractor, once the agency becomes aware of that subcontractor’s experience . . . it cannot reasonably assign one proposal a higher score than another based on that experience.” GAO nevertheless denied the protest.

The Small Business Administration is continuing the task of implementing several regulatory changes required by the National Defense Authorization Act for Fiscal Year 2013 (NDAA) [pdf]. One such change occurred on May 7th when the SBA published an interim final rule (RIN 3245-AG55) [pdf] enacting section 1697 of the NDAA and amending 13 CFR 127.503 [pdf]. The interim final rule removes  the statutory cap on set-aside contracts for Women Owned Small Businesses (WOSB) and Economically Disadvantaged Women Owned Small Businesses (EDWOSBs).

Flight delays resulting from the furloughs of air traffic controllers are certainly not the only impact of sequestration. All federal contractors and grant recipients will have to adapt to reduced federal spending. According to the OMB report to Congress on sequestration reductions for FY 2014, $109 billion will be cut from the federal budget next year with equal reductions of approximately $54.7 billion in the defense and non-defense categories. Discretionary defense spending will see a $53.9 billion reduction, while direct defense spending will be reduced by $749 million. Non-defense discretionary spending will decrease by $37.2 billion, and non-defense direct spending will shrink by $17.5 billion, $11.2 billion of which will come from reductions in Medicare spending.

As agencies struggle with these mandatory budget cuts imposed by sequestration, incrementally funded contracts are particularly vulnerable. Despite the apparent need for their goods or services and the high caliber of their work, contractors holding incrementally funded contracts may find that funds are simply not available. Here are three strategies contractors can take to limit the risk of performing without compensation: