FAR 52.242-14; liquidated damages; remission of liquidated damages

If you are getting ready to submit a claim on a federal contract—especially one that challenges an assessment of liquidated damages—take note of the Federal Circuit’s decision in K-Con Building Systems, Inc. v. United States, No. 2014-5062 (Fed. Cir. Feb. 12, 2015) [pdf]. It has some specific instructions for the contents of your claim letter and demonstrates the harsh results that follow from a misstep in the disputes process.

K-Con held a Federal Supply Schedule contract for prefabricated structures. In 2004, it won a $582,000 Coast Guard task order for the design and construction of a Coast Guard cutter support building at Port Huron, Michigan.

K-Con’s July 2005 Claim

When K-Con was unable to complete the work by the deadline set forth in the task order, the Coast Guard assessed liquidated damages of $109,554—186 days at $589 per day. On July 28, 2005, K-Con submitted a one-page claim letter seeking remission of the liquidated damages.

Although it was brief, K-Con’s letter asserted three reasons why the liquidated damages assessment was improper:

  1. K-Con “was not the sole cause of any alleged delays” and any K-Con delays were “concurrent with delays caused by the government;”
  2. the government “failed to issue extension to the completion date as a result of changes to the contract by the government;” and
  3. the liquidated damages “are an impermissible penalty.”

K-Con’s letter requested a contracting officer’s final decision. Though it demanded relief of more than $100,000, K-Con’s letter asserted that a certification was not required “since the assessment of liquidated damages is a claim by the Government.”