If you are excluded from the competitive range in a procurement, you have a right to request a debriefing (within 3 days) to learn why. 41 U.S.C. § 3705(a). But the scope of that pre-award debriefing is more limited than a post-award debriefing. Pre-award debriefings cover the agency’s evaluation of “significant elements” of the excluded contractor’s offer, the rationale for the exclusion, and “reasonable responses to relevant questions” posed by the excluded offeror. 41 U.S.C. § 3705(d). But they expressly cannot cover the total number or identities of offerors, or the “content, ranking, or evaluation” of the other offerors’ proposals. 41 U.S.C. § 3705(e). That information is available only in post-award debriefings. 41 U.S.C. § 3704(c). This difference in scope may create the temptation to delay a pre-award debriefing until after award in the hope that you will gain more information. But giving in to that temptation may preclude a protest at GAO.
pre-award protest
Bid protests in Virginia
Contracts with Virginia agencies, counties, municipal governments, and school boards are governed by the Virginia Public Procurement Act. The Act requires the use of competitive procedures in the solicitation and award of public contracts. It also establishes a procedure for the submission and resolution of bid protests. See Va. Code Ann. § 2.2-4360(A).
How and when to protest a contract award decision
An actual or prospective bidder seeking to challenge the award of a Virginia government contract must submit a protest to the procuring agency or to an official designated by the agency. The protest must be submitted in writing. It must include the basis for the protest and the relief sought. A bid protest must be submitted no later than ten days after the award or the announcement of the decision to award, whichever occurs first. This deadline is extended if the protest depends on obtaining access to documents. In those situations, the protest must be submitted within ten days after the records are made available. The VPPA does not specifically allow for the submission of a pre-award protest that challenges the terms and conditions of a solicitation.
If a protest is timely filed, the award and performance of the contract is automatically stayed unless the agency determines in writing that “proceeding without delay is necessary to protect the public interest or unless that bid or offer would expire.” Va. Code Ann. § 2.2-4362.