Photo of Ken Slavens

Ken represents architects, engineers, owners and contractors in various construction disputes, including claims for defective design and construction, delay allegations, cost overruns, interference, obstruction, property damage and suspension of work. He litigates claims arising from injuries on project sites or from defective construction.

Arbitration is often seen as a way of getting a more predictable result in complex construction disputes. The subject matter expertise available with experienced arbitrators and the finality of the arbitration process itself are certainly important considerations. But resolving disputes in arbitration can sometimes lead to surprising results, even ones that might be inconsistent with the underlying contract or with applicable state law.

The Eighth Circuit’s recent decision in Beumer Corp. v. ProEnergy Services, LLC, No. 17-2862 (8th Cir. Aug. 9, 2018), is an example of such a case. The arbitrator in this case awarded attorney’s fee of nearly a million dollars more than the liability cap in the contract. Despite the possibility that this result was inconsistent with state law, the Eighth Circuit let the award stand.

In Joe Tex’s song about unrequited love, the Southern Soul singer belts out, “I gotcha, never shoulda promised to me.” Joe Tex may have thought this approach is the right one for romantic disappointment, but parties to a contract have a different set of obligations.

A lawsuit by Washington State contractor Nova Contracting should serve as an alert to owners dealing with the assessment of a contractor’s performance. Nova’s lawsuit came about because of the owner’s termination of the contract. Nova claimed the owner was using a “gotcha” review process for its submittals that was designed to prevent performance. The trial court agreed with the owner.

Nova appealed and the court of appeals found sufficient questions of fact to send the dispute back to the trial court. The opinion offers insight into fair dealing and good faith in the performance of construction contracts. Nova Contracting, Inc. v. City of Olympia, No. 48644-0-II (Wash Ct. App. Apr. 18, 2017).

Claims for personal injuries that can be connected in some way to construction work often include allegations that the contractor was negligent. Even if the injured party sues only the property owner, the owner will often seek to pass this liability through to the contractor. In many states, such negligence claims are barred by the acceptance doctrine, which limits contractor liability to third parties for injuries that occur after the owner has accepted the work.

A recent decision by the Missouri Court of Appeals illustrates and applies this rule. In Wilson v Dura-Seal and Stripe, Inc., No. ED 104570 (Mo. Ct. App. Mar 21, 2017), the plaintiff alleged that she tripped in an area paved by Dura-Seal and Stripe, Inc. Dura-Seal paved a drive lane, but the paving did not extend all the way to the curb. The result was a gutter area and a resulting height differential. Ms. Wilson claimed she tripped on and because of the height differential.  Ms. Wilson sued the school district for which Dura-Seal did the work. The school district then sued Dura-Seal.

The trial court granted summary judgment for Dura-Seal because the work had been accepted. The court of appeals affirmed. Under Missouri law, a contractor is not liable for third party personal injuries after the owner accepts the work. The acceptance doctrine is founded on the assumption that the owner has made a reasonably careful inspection of the work of the contractor and the owner knows of the defects, if any. The owner then “accepts the defects and negligence that caused them as his own.”

The Missouri Court of Appeals decision in Penzel Constr. Co. v. Jackson R-2 School District, No. ED103878 (Mo. Ct. App. Feb. 14, 2017), is an important development for public construction contracting in Missouri. The decision adopts the Spearin Doctrine and approves the use of the Modified Total Cost method for proving damages. While these concepts have been used widely in federal construction contracting, the Penzel decision is the first published decision recognizing them in Missouri.

The Penzel case involved additions to a public high school. The School District hired an architect. The architect retained an electrical engineering sub-consultant. When the project went to bid, the School District furnished bidders with the architect’s plans and specifications. Penzel Construction Company submitted a bid as the general contractor.

Penzel’s electrical subcontractor was Total Electric. Total’s bid was $1,040,444. Neither Penzel nor Total “noticed” any errors, omissions, or other problems with the plans and specifications during the bidding process.

Total encountered delays totaling 16 months, which Total attributed to “defects and inadequacies” in the electrical design. Under a liquidating agreement between Penzel and Total, Penzel sued the District. Penzel alleged that the District impliedly warranted the design. Penzel claimed the design was not adequate for completing the project.

In addition to proving liability, Penzel needed to prove the damages associated with its loss of productivity claim. To do so, Penzel sought to use the Modified Total Cost Method. The claimed damages were comprised of additional project management and supervision costs, wage escalation, unpaid change order work, and consultant’s fees.