The automatic stay of award is one of the key elements of a bid protest under the Competition in Contracting Act. The CICA stay is only available when a protest is filed no later than ten days after contract award or no later than five days after a debriefing. In the 2018 NDAA (Section 818), Congress introduced the enhanced debriefing process for DoD procurements. It allows disappointed offerors to submit follow-up questions within two business days after a debriefing. It also extends the protest deadline until those questions are answered. But what if the contractor does not have any additional questions? Does the two-day period to submit questions extend the protest deadline for purposes of the CICA stay?

The Federal Circuit answered this question in NIKA Technologies, Inc. v. United States, Case No. 2020-1924 (Feb. 4, 2021). If a contractor does not submit follow-up questions after a debriefing, it does not get the benefit of the two-day question period for purposes of the CICA stay.

Refresher on protest deadlines

 The automatic stay applies if a protest is filed on or before the later of: (i) ten days after contract award; or (ii) five days after “the debriefing date” that is offered to an unsuccessful offeror (when a debriefing is required and requested). 31 U.S.C. § 3553(d)(4). The “debriefing date”  was the date that the agency offered to meet with the disappointed offeror or the date it provided a written debriefing. Protesters seeking to obtain a CICA stay knew that the 5-day clock began to run on these dates. [NOTE: The CICA stay protest deadlines are separate from GAO’s deadlines for timely protests in 4 C.F.R. § 21.2.]

Enhanced debriefings can extend the protest deadline for a CICA stay on DoD procurements. The revised statute requires that the “debriefing” include a two-business-day period to ask follow-up questions:

The debriefing shall include, at a minimum—

*          *          *

(vii) an opportunity for a disappointed offeror to submit, within two business days after receiving a post-award debriefing, additional questions related to the debriefing.

If the offeror submits follow-up questions, the agency must respond within five business days, and it “shall not consider the debriefing to be concluded until the agency delivers its written responses to the disappointed offeror.” These requirements are codified at 10 U.S.C. § 2305(b)(5)(C). If an offeror timely submits follow-up questions, the “debriefing date” is extended until the agency answers those questions.

But what if there are no follow-up questions? Is the “debriefing date” extended by two days to account for the question period?

No extension if there are no follow-up questions

This is the question addressed in NIKA Technologies, which involved a Corps of Engineers procurement for the Operation and Maintenance Engineering Enhancement program for DoD medical facilities. Here’s what happened in that case:

  • On February 27, the Corps found that NIKA’s proposal was unacceptable. NIKA timely requested a debriefing the next day.
  • On March 3, NIKA submitted an initial set of debriefing questions to the Corps.
  • On March 4, the Corps provided NIKA with a written debriefing letter and provided answers to NIKA’s questions. The Corps’ March 4 letter stated that it would “consider the debriefing closed if additional questions are not received” within two business days. If questions were received, the letter stated that the debriefing would be considered closed “upon delivery of written response to any additional questions.”
  • On March 5, NIKA advised the Corps that it was reviewing the Corps’ debriefing letter and its answers to the first set of debriefing questions.
  • On March 7, NIKA advised the Corps that it did not have any follow-up questions.
  • On March 10, NIKA filed its protest with the GAO.

The Corps refused NIKA’s request for an automatic stay. The Corps argued that NIKA’s protest was filed outside the 5-day CICA deadline. Because NIKA did not submit any follow-up questions, the Corps argued that NIKA’s debriefing closed on March 4.

NIKA challenged that decision in the Court of Federal Claims. See NIKA Technologies, Inc. v. United States, Case No. 20-299C (Apr. 21, 2020). NIKA argued that its debriefing remained open for the two-day question period under 10 U.S.C. § 2305, and that its “debriefing date” for purposes of the CICA stay was March 6, not March 4. The Court of Federal Claims agreed with NIKA.

The Government then appealed the COFC decision to the U.S. Court of Appeals for the Federal Circuit. (NIKA did not participate in the appeal because its protest had already been resolved.) The Federal Circuit reversed the COFC, holding “the debriefing is not automatically held open for an additional two days” to allow for the submission of follow-up debriefing questions. In its view, the plain meaning of “the debriefing date” in 31 U.S.C. § 3553 is that “the clock starts on the day that the bidder receives debriefing.” If Congress meant the deadline to run from the “end of the debriefing process,” as the COFC found when ruling for NIKA, Congress could have said so.

The Federal Circuit also found support for its view in 10 U.S.C. § 2305, which describes the two-day question period occurring “after receiving a post-award debriefing.” This “means that the two-day period for questions occurs within the five-day window for filing a protest.” If questions are submitted, the debriefing is extended. “By implication, when there are no additional questions submitted, as here, the debriefing period is not held open.” Since NIKA did not ask follow-up questions, its debriefing date was March 4 and its protest, filed on March 10, was filed one day too late to obtain an automatic stay of award under CICA.

The Federal Circuit’s decision makes it clear that disappointed bidders seeking to take advantage of the additional time offered by an “enhanced debriefing” on DoD procurements must ask at least one follow-up question.