The automatic stay of award is one of the key elements of a bid protest under the Competition in Contracting Act. The CICA stay is only available when a protest is filed no later than ten days after contract award or no later than five days after a debriefing. In the 2018 NDAA (Section 818), Congress introduced the enhanced debriefing process for DoD procurements. It allows disappointed offerors to submit follow-up questions within two business days after a debriefing. It also extends the protest deadline until those questions are answered. But what if the contractor does not have any additional questions? Does the two-day period to submit questions extend the protest deadline for purposes of the CICA stay?
The Federal Circuit answered this question in NIKA Technologies, Inc. v. United States, Case No. 2020-1924 (Feb. 4, 2021). If a contractor does not submit follow-up questions after a debriefing, it does not get the benefit of the two-day question period for purposes of the CICA stay.