The U.S. Postal Service spends about $3 billion per year to move the mail by truck and does so under a special type of contract called a Highway Contract Route (HCR) contract. These contracts have unique contract clauses, and even their own lingo. For example, an HCR “amendment” is what the rest of the government contracting world would call a contract “modification.”

One of the biggest differences between HCR contracts and other government contracts is the Changes clause. Under an HCR contract, the contracting officer has limited ability to direct unilateral changes. The CO may only issue a unilateral change, called a “minor service change,” if the price impact would be $5,000 or less. Under a Contract Delivery Service (CDS) contract – a subset of HCR contracts for mailbox deliveries – unilateral changes must be $2,500 or less. Even for these changes, a contractor who disagrees with the CO’s determination may file a claim for additional compensation.

In addition to these monetary thresholds, unilateral changes are further restricted to certain types of changes. The only unilateral changes a CO can direct are an extension, a curtailment, a change in line of travel, a revision of route, and an increase or decrease in frequency of service or number of trips. The CO has no authority to unilaterally direct any other change, even if the price impact would be $5,000 or less. For example, the contracting officer may not unilaterally direct a contractor to change equipment or buy new equipment.

Every government contract contains implied duties, such as the duty to cooperate and the duty of good faith and fair dealing. Such implied duties generally prohibit one party from interfering with the other’s performance or taking actions that undermine the other’s expected benefit of the bargain.

Implied duties offer important protections when an issue is not clearly addressed in the text of the agreement. But courts have been reluctant to apply them in a way that overrides express contract language. A party generally does not breach the duty of good faith and fair dealing, for example, simply by exercising a right that is expressly provided in the contract.

But the government does not have carte blanche. Even if there is express language that gives the government a certain right, the government cannot exercise that right unreasonably or in a way that interferes with the contractor’s performance. In Agility Public Warehousing Company KSCP v. Mattis, No. 2016-1265 (Fed. Cir. Apr. 4, 2017), for example, the Federal Circuit explained that the government can breach the duty of good faith and fair dealing even if its conduct is otherwise consistent with the express terms of a contract.

Claims for personal injuries that can be connected in some way to construction work often include allegations that the contractor was negligent. Even if the injured party sues only the property owner, the owner will often seek to pass this liability through to the contractor. In many states, such negligence claims are barred by the acceptance doctrine, which limits contractor liability to third parties for injuries that occur after the owner has accepted the work.

A recent decision by the Missouri Court of Appeals illustrates and applies this rule. In Wilson v Dura-Seal and Stripe, Inc., No. ED 104570 (Mo. Ct. App. Mar 21, 2017), the plaintiff alleged that she tripped in an area paved by Dura-Seal and Stripe, Inc. Dura-Seal paved a drive lane, but the paving did not extend all the way to the curb. The result was a gutter area and a resulting height differential. Ms. Wilson claimed she tripped on and because of the height differential.  Ms. Wilson sued the school district for which Dura-Seal did the work. The school district then sued Dura-Seal.

The trial court granted summary judgment for Dura-Seal because the work had been accepted. The court of appeals affirmed. Under Missouri law, a contractor is not liable for third party personal injuries after the owner accepts the work. The acceptance doctrine is founded on the assumption that the owner has made a reasonably careful inspection of the work of the contractor and the owner knows of the defects, if any. The owner then “accepts the defects and negligence that caused them as his own.”

Similar to a Termination for Convenience clause, a Termination with Notice clause (often found in U.S. Postal Service contracts) allows a party to end a contract without breaching it. Under the clause, either party may terminate the contract without cost consequences by providing advance written notice – usually 60 days – to the other party. The Postal Service Board of Contract Appeals (PSBCA) addressed the limits that apply to the exercise of this clause in a decision on two closely related cases. Cook Mail Carriers, Inc., PSBCA No. 6583, and Patricia Joy Sasnett, PSBCA No. 6584, issued on March 24, 2017.

Cook and Sasnett each had separate Highway Contract Route contracts to transport mail at designated times between various points in Alabama. In March 2014, the Postal Service made changes to its processing network that affected several contractors, including Cook and Sasnett. While the network changes could have been effected by modifying their contracts, the Contracting Officer (CO) instead exercised the Termination with Notice clause.

When he terminated the contracts, the CO misunderstood the network changes.  He thought the changes were needed because the Gadsden, AL mail processing facility was closing.  In fact, the Gadsden facility was already closed and revised routes were needed because other mail transportation hubs were being relocated.

Propriety of the termination

Cook and Sasnett filed claims asserting the terminations were improper and the case ended up at the Postal Service Board of Contract Appeals (PSBCA). Examining the Termination with Notice clause, the PSBCA noted that while it does not include any express limitations, its use “is not truly unlimited.”  The PSBCA then considered whether the CO’s action was proper under three separate legal principles.